- All work on this 100 MGD facility had to be completed around an existing, operational plant over a three-year period.
- Our process piping scope included upgrades to all chemical systems, methanol piping, aeration piping and process wastewater.
- The project included several thousand feet of stainless steel, FRP, PVC and ductile iron pipe. Prefabrication was completed in our own Newburgh shop.